In short
Emptying frequency depends on sludge accumulation, not just the time since the last visit. In France, for a fosse toutes eaux (tank receiving all household wastewater), arrange for an approved contractor to empty it before sludge exceeds 50 % of its usable volume. For a micro treatment plant or another approved treatment system, follow the manufacturer's guide and ask SPANC (local public service that inspects non-collective sanitation) for advice if you are unsure.
- For a tank receiving all household wastewater, sludge level determines when emptying is needed. It must not exceed 50 % of the usable volume.
- Odours, slow drainage or sewage backing up warrant a check, but do not by themselves prove that emptying is needed.
- SPANC checks the maintenance of the installation, notably using the slip issued by the approved emptying contractor.
Determining the emptying frequency from the sludge level
A septic tank receiving all household wastewater normally contains liquid during operation. The liquid level alone therefore does not tell you whether emptying is needed. Sludge settles at the bottom and gradually builds up. You need to assess how much space it occupies in the tank, not simply whether water is present.
In France, the 50 % reference point concerns the usable volume occupied by sludge. It does not mean you should wait until the tank is half full of liquid. The tank must be emptied before the sludge exceeds this threshold. A measurement taken by a professional will show where the system stands in relation to this reference point.
How often the property is occupied and how the system is used affect sludge build-up. An occasionally occupied property does not receive the same wastewater inputs as a permanently occupied home. New occupants or heavier use can also change the rate of build-up. Simply repeating the interval between previous emptying visits is therefore not enough.
Ask a professional to check the sludge level and explain the result. Tell them about any changes in occupancy and your usage habits. Do not open the tank or try to measure the sludge level yourself: gases and the risk of falling make this dangerous. If you do not know your tank’s specifications, ask the SPANC (local public service that inspects non-collective sanitation) to help you identify the applicable reference point.
Check the instructions for your installation
The term “septic tank” is often used to describe different installations. A septic tank receives wastewater from toilets. An all-wastewater tank also receives wastewater from the kitchen and bathroom. These tanks provide preliminary treatment before further treatment. A micro treatment plant treats wastewater using a biological process specific to the system.
This distinction matters for maintenance. Do not automatically apply instructions for an all-wastewater tank to a micro treatment plant. For micro treatment plants and other systems approved in France, consult the manufacturer’s user guide for the installed model. It sets the emptying frequency and specifies the maintenance tasks required.
To find the right instructions, gather the available documents:
- the user guide supplied when the system was installed;
- the model reference and the manufacturer’s name;
- the installation file and the latest report from the SPANC (local public service that inspects non-collective sanitation).
If the guide is missing, ask the manufacturer for a copy that matches your equipment. Instructions for another model are not enough to decide how to maintain it.
Not sure which system is installed at the property? Contact the SPANC with the documents you have. Ask them to help identify the installation and confirm the applicable instructions. Then pass this information to the emptying contractor so they can prepare for work suited to the system.
What signs mean you should request a check?
Unusual smells in the house or near the tank, slow drainage and sewage backing up should prompt you to request a check. These signs may indicate a fault. On their own, they do not prove that the tank needs emptying.
Note what has changed before contacting a sanitation company:
- Are the smells in one room or outside?
- Is drainage poor from just one fixture or from several?
- Does sewage back up every time you use the fixture, or only occasionally?
These observations will help the contractor narrow down the cause. A blocked pipe, a ventilation problem or a fault elsewhere in the system could also be responsible. Emptying alone will therefore not necessarily solve the problem. Ask the contractor to identify the cause before deciding on the right action.
If sewage backs up, limit use of the affected fixtures and contact a company straight away. Avoid all contact with wastewater. Never enter a tank or lean over an opening to find the source of a smell: dangerous gases may be present.
Conversely, the absence of smells or slow drainage does not guarantee that maintenance can wait. Keep checking the system regularly rather than relying on these warning signs alone. If you are unsure about the right monitoring and maintenance for your system, ask your SPANC (local public service in France that inspects non-collective sanitation) for advice.
What does the SPANC check during its inspection?
In France, the service public d’assainissement non collectif (SPANC, local public service that inspects non-collective sanitation) checks that systems not connected to the public sewer network are working properly and maintained. During its visit, it checks, among other things, that emptying has been carried out by an approved operator. The slip given to the owner serves as proof of this work.
The inspection frequency is not the same as the emptying frequency. Each system must be inspected at least once every 10 years. The commune (municipality) or intercommunalité (group of municipalities) sets the exact frequency in its area. To find out which frequency applies to your home, contact your SPANC or local authority.
This inspection schedule is therefore not a maintenance schedule. You should not wait for the next SPANC visit to have a system emptied if it needs it. Equally, an upcoming inspection does not automatically mean that emptying is necessary.
The emptying contractor and the SPANC have separate roles. The contractor carries out the work and provides the bordereau de suivi des matières (waste tracking slip). The contractor does not replace the SPANC and cannot issue the inspection report required when a property is sold on its behalf.
As the owner, keep your copy of the slip, signed by both you and the emptying contractor. The SPANC will ask for it to check that emptying has been carried out. Before the inspection, ask the service which other documents to prepare so that you can provide the relevant information about your system and its maintenance.
Arranging the next emptying and keeping the records
Before booking an appointment in France, check the list of approved septic tank emptying contractors published on the préfecture (local office of central government) website. Check the company’s name, approval number and approval expiry date. If you cannot find this information, ask the préfecture for confirmation.
Prepare the information the contractor will need: the installation’s address, tank type, capacity if known, location of access points and any access restrictions for the truck. Also find the previous bordereau de suivi (waste tracking slip) and the installation documents. Report any changes in occupancy of the property and any problems noticed since the last visit.
After emptying, collect your copy of the bordereau de suivi, signed by both you and the contractor. File it with previous records and documents from the SPANC (local public service that inspects non-collective sanitation). This slip provides evidence of maintenance: do not keep only the invoice.
Then agree on follow-up based on the contractor’s observations. Ask them to record any details useful for preparing the next visit and to specify when the installation should be checked again. Avoid simply repeating a fixed interval without considering its condition and use. If you are unsure what follow-up is needed, contact the SPANC.
For sanitation companies, HydraPlus makes tracking slips available to customers in their online account and allows an automatic reminder to be sent for the next emptying.
Frequently asked questions
How often should a septic tank be emptied?
There is no single schedule. In France, for a fosse toutes eaux (a septic tank receiving all household wastewater), the key measure is the amount of accumulated sludge, which must stay below 50 % of the usable volume. Have a professional assess this level and ask the SPANC (local public service that inspects non-collective sanitation) for guidance specific to your system.
What are the signs that a septic tank needs emptying?
Unusual smells, slow drains or sewage backing up mean you should arrange a check. These signs alone do not prove that the tank needs emptying. A professional must identify the cause and check the sludge level.
Does a small wastewater treatment plant need emptying as often as an all-wastewater septic tank?
The guideline for an all-wastewater septic tank should not automatically be applied to a small wastewater treatment plant. Check the manufacturer's user guide for the specified emptying frequency and ask the SPANC to confirm the guidance if you are unsure.
Can I empty my septic tank myself?
In France, emptying, transport and disposal of the waste must be carried out by a person approved by the préfet (the local representative of the French state). To choose a contractor, consult the list of approved persons published on your préfecture (local French state administration) website.
What document should I keep after septic tank emptying for the SPANC?
Keep your copy of the bordereau de suivi (waste tracking slip), signed by you and the emptying contractor. It provides proof of maintenance to the SPANC. This document does not replace the inspection report issued by that service.
Next step
See HydraPlus on your own jobs in France
Scheduling, job sheets, waste tracking slips and invoices for sanitation companies operating in France. The software and the demo are in French.
Official French texts and sources
- Portail interministériel de l'assainissement non collectif (interministerial portal for non-collective sanitation) (in French)
- Arrêté du 27 avril 2012 (inspection of non-collective sanitation installations) – Légifrance (in French)
- Arrêté du 7 septembre 2009 modifié (amended order on approval of septic tank emptying contractors) – Légifrance (in French)
Further reading (in French)